Flow 01
Project setup and budget
The contract sum, its breakdown and the cost budget are what every later claim, variation and forecast is measured against. When they live in a tender spreadsheet that drifts from what was signed, claims are measured against the wrong values and nobody can say what margin was won at award.
- Starts when
- A letter of award or contract is signed for a new project.
- Ends with
- A project with a locked original contract sum, contract items and cost budget by cost code, contract terms with clause references, a claim calendar, and empty registers for variations, subcontracts, claims and retention.
- 1.Person: Contracts manager
Creates the project from the letter of award with the client, contract sum, dates and payment terms.
- Contract sum before GST must equal the letter of award figure.
- Retention rate and cap, defects liability period, claim cut-off day, payment response period and payment period are entered with the clause number each comes from.
- Each subcontract and PO is later tagged as a construction contract or a supply contract, because the Act sets different response and due date rules for each.
- 2.Person: Quantity surveyor
Imports the priced BOQ or schedule of values as the contract items the client's QS will certify against.
- The sum of contract items must equal the contract sum to the cent, or the import is rejected.
- Provisional sums and prime cost sums are typed separately, since they are adjusted against actual cost and are not claimed by percentage.
- For a schedule of rates contract, items hold a rate and an estimated quantity, and claims are measured quantity times rate.
- 3.Person: Quantity surveyor
Maps each contract item to the cost codes that carry its cost.
- Every contract item needs at least one cost code before the project can be approved.
- Cost codes come from the company list; a new code needs the commercial manager.
- Subcontract scopes are mapped to the same contract items, so a subcontractor's claim can be compared with site progress on the same items later.
- 4.Person: Project manager
Sets the cost budget by cost code from the estimator's tender cost build-up.
- Each budget line keeps the estimator's basis (quantity and rate), so later variances can be traced to a quantity or a rate.
- Contract sum minus total budget gives the margin at award; a margin below the company minimum needs the director's approval with a note.
- 5.Person: Project director
Approves the baseline of contract items, cost budget and contract terms.
- After approval the original contract sum and original budget are locked; they change only through approved variations and logged budget revisions.
- The approval is logged with the approver, the time and the baseline version.
- 6.System: System
Builds the claim calendar and opens the project to site updates, requisitions and the progress claim agent.
- Each claim date carries its payment response due date and payment due date, shown with the clause reference so the contracts manager can check them.
- The progress claim agent gets read access to the approved baseline only; it cannot change contract items, the contract sum or the budget.
Exceptions
- The BOQ total does not match the signed contract sum, for example after a negotiated discount
- The QS adds the difference as its own adjustment item instead of spreading it across rates, so the items still add up to the signed sum when every item reaches 100%.
- The client's QS uses a different breakdown from the tender BOQ
- The client's breakdown becomes the contract items, because that is what gets certified, and the tender lines are kept only as the budget basis behind the cost codes.
- Work starts on a letter of intent before the contract is signed
- The project opens with a letter of intent status and a ceiling value. Requisitions and site updates are allowed up to the ceiling; any claim needs the project director until the baseline is approved.
- The budget gives a margin below the company minimum
- The project cannot be approved by the project director alone. The director approves with a written reason, and the project starts on the forecast watch list.